Kitchen floor and wall texture cleared before a family room addition
Example project
- Home
- 1970s two-story tract house in Huntington Beach with a galley kitchen at the back
- Original request
- Add a family room off the kitchen, opening the wall between the two
- Testing
- A Cal/OSHA-certified asbestos consultant samples the kitchen sheet vinyl, the wall texture on both sides of the opening and the ceiling texture
- Found
- Asbestos in the sheet vinyl with its backing and in the texture on the wall being opened
- Clear
- The ceiling texture
- Area
- About 180 sq ft, 120 of floor and 60 of wall
- Timeline
- Notice no later than 10 working days ahead, then two working days
- Cost
- $3,600
Scope of work
Lab results for each material, the district notice, the kitchen sealed with air filters running, wet removal of the vinyl and the wall texture into labeled bags and the haul. The survey, the clearance air test, the new wall opening and the addition itself are separate.
Project overview
In this example, a Huntington Beach family is adding a family room behind the kitchen of their 1970s house. The wall between the two is load-bearing, and taking out a load-supporting wall counts as demolition, so the district notice is required whatever the amount of material.
The owner pulls the permit as owner-builder and signs the city’s Permit & Asbestos Disclosure at issuance. That form is a promise to notify the district and have a consultant survey if needed, and here both are done. The abatement crew then removes the positive floor and wall texture before the framers start.
The goal
The goal is a kitchen with the positive floor and wall texture gone, so the framers can open the wall to the addition.
Process
- First visit A Cal/OSHA-certified asbestos consultant samples the kitchen floor, both sides of the wall and the ceiling.
- Before work The abatement contractor files the district notice online, and the owner signs the disclosure when the permit is issued.
- Days one and two The kitchen is sealed, the vinyl and the wall texture come off wet, and the bags are hauled.
- Last An independent consultant tests the air, and the framers open the wall.
Planning right
- Move the kitchen contents out before the consultant visit.
- Keep the district notice and the lab report with the permit papers.
- Ask the framers to wait for the air results.
- Plan meals away from the kitchen for the work days.